General Mills Case Study
Wastewater Treatment System
Covington, Georgia
Covington, Georgia
Job Details
- Installed an equalization system
- Constructed a new building for the wastewater treatment system equipment
- Installed a Bioreactor with Membrane Filtration and Reverse Osmosis (RO) Treatment
- Installed a water reuse system
- Installed all interconnecting pipe
- Installed a chemical feed and sludge processing system
- Installed controls and wiring
Project Location: | Covington, GA |
Project Cost: | $5,387,636.00 |
Date Completed: | August, 2006 |
Owner: | General Mills |
Engineer: | GRW |